HV Infrastructure Improvement, Substation and New Paediatric supply
HV Infrastructure Improvement, Substation and New Paediatric supply
Operational NHS General Hospital Site
The Objectives
- Provide new high voltage (HV) substation to provide new low voltage electrical supply for new paediatric building at major General Hospital.
- Ensure compliance with HTM guidance for primary and secondary stand by generator supplies
- Deliver a future HV infrastructure
- Conduct a feasibility study to enable optimised improvements for future distributed operational HV ring capacity and HV system resilience
- Optimise equipment selection, HV route divergence and removal of aged services
- Resilient new low voltage distributed supply and optimised equipment design and specification for the new building
- Minimise risk whilst completing works including replacement of one of the two existing hospital HV ring feeders
- Meet the target completion for both the primary and secondary low voltage (LV) supplies for the new paediatric unit
- Provide energy monitoring to assist in managing carbon reduction
Challenges
- It was imperative that the completed system complied with the constraints of HTM06-01 (HV) and HTM06-03
- Maintaining safely managed and consistent best practice project delivery in line with client expectations in a politically challenging and cost-conscious environment
- Identify unknown service routes through GPR ground, HV cable tracing and structural surveys
- Determine optimal new HV and LV cable routes, minimising risk to existing congested underground services and day to day operational service delivery within a busy General Hospital during project works
- Excavation of cable routes and major equipment deliveries within blue light roads and adjacent to the new build construction site
The Successful Solution
- Determined optimised HV transformer capacity, incorporating close coupled LV isolation for ease of future Hospital Estates in house control
- Constructed a flexible base HV sub-station, accommodating ease of future additional LV distribution and HV reconfiguration if required
- Construction of adjacent compound for low noise 1MVA secondary power generator
- Local LV distribution/generator changeover panel incorporating withdraw able replicated breakers for ease of replacement in the event of breaker failure
- LV panel construction accommodating non-invasive inspection to minimise planned service down time, increasing system resilience as inspections can regularly be conducted to identify problems before they occur
- Secure generator compound construction, accommodating revised pedestrian routes and safe egress from the newly constructed adjacent ambulance bay
- LV distribution incorporating full remote monitoring capability via BMS or mobile GPRS network on almost any device, complete with secure data capture and storage for better power management
- Provided temporary LV supply to new paediatric unit site during the build to permit Paediatric commissioning to be undertaken without delay
- Successful project management throughout with architects, generator and electrical distribution equipment manufacturers, Clients teams, new building construction and M&E install teams, crane delivery teams and ambulance management for agreed finalised mains connection on target to meet building handover date
Thanks to all who played a part in the team effort required to deliver this challenging healthcare project.